File No. 2222 Board Order No. 2222-2 February 4, 2025

SURFACE RIGHTS BOARD

IN THE MATTER OF THE PETROLEUM AND NATURAL GAS ACT, R.S.B.C., C. 361 AS AMENDED

AND IN THE MATTER OF THE NORTH WEST ¼ OF SECTION 25, TOWNSHIP 80, RANGE 15, WEST OF THE 6TH MERIDIAN PEACE RIVER DISTRICT

BETWEEN:

AND:

(The "Lands")

Vermilion Energy Inc.

Dorothee Walburga Luise Huenseler

(APPLICANT)

(RESPONDENT)

____________________________________ BOARD ORDER _____________________________________

VERMILION ENERGY INC. v. HUENSELER ORDER 2222-2 Page 2

Vermilion Energy Inc. (“Vermilion”) seeks a right of entry order to access certain lands legally owned by Dorothee Walburga Luise Huenseler to carry out an approved oil and gas activity, namely the construction, operation and maintenance of a flow line and other associated infrastructure.

The Surface Rights Board orders that:

ORDER

1.

2.

3.

4.

Upon payment of the amount set out in paragraphs 2 and 3, Vermilion shall have the right of entry to and access across the portions of the lands shown outlined in red on the Individual Ownership Plan attached as Appendix “A” (the “Lands”) as necessary for the purpose of constructing, operating and maintaining a sour gas flow line (referenced as segment 004) and other associated infrastructure in accordance with BCER Permit No. 100119733.

Vermilion shall pay to the landowner as partial compensation the amount of $10,000.

Vermilion shall deliver to the Surface Rights Board security in the amount of $2,500 by cheque made payable to the Minister of Finance. All or part of the security deposit may be returned to Vermilion, or paid to the landowner, upon agreement of the parties or as ordered by the Board.

Nothing in this order operates as a consent, permission, approval, or authorization of matters within the jurisdiction of the BC Energy Regulator.

DATED: February 4, 2025 FOR THE BOARD

Peter Judd, Mediator

VERMILION PIPELINE R/W PLAN EPP79722

SCHEDULE "A"

Attached to and made part of this Agreement dated this______day of _________________, 20_____, between Dorothee Walburga Luise Huenseler (Grantor) and Vermilion Energy Inc. (Grantee). PROPOSED SW 1/4 10 x 28m SEC 36 TOURMALINE PIPELINE R/W WORKSPACE (AD No.: 100100344) (0.069 ac) PROPOSED PROPOSED 0.05ha 5 x 67m WORKSPACE WORKSPACE (0.128 ac) (0.084 ac) PROPOSED PROPOSED 10 x 58m 10 x 97m WORKSPACE WORKSPACE (0.143 ac) (0.240 ac)

CNRL PIPELINE R/W PLAN 27613

TOURMALINE PIPELINE R/W (AD No.: 100100344)

PROPOSED 30 x 40m DECKING SITE (0.296 ac)

PROPOSED 10 x 258m SHOOFLY (0.637 ac)

TOURMALINE PIPELINE R/W (AD No.: 100108648)

TOURMALINE PIPELINE R/W (AD No.: 100106633)

Certified correct this 4th day of April, 2024.

AREAS

Permanent Temporary Total

1.658 ha 1.095 ha 2.753 ha

PROPOSED 3 x 625m

WORKSPACE (0.462 ac)

PROPOSED 5 x 191m WORKSPACE (0.237 ac)

N

Page __ of __

PROPOSED 10 x 59m WORKSPACE NW 1/4 (0.146 ac) SEC 25 TOWNSHIP 80 RANGE 15 W6M PROPOSED 20 x 829m PIPELINE R/W (4.097 ac)

PROPOSED 10 x 107m WORKSPACE (0.264 ac)

4.097 ac 2.706 ac 6.803 ac

Owner(s): Title No.: Parcel Identifier: Landowner File: Vermilion File:

Andrew J. Moody

TOURMALINE PIPELINE R/W (AD No.: 100100447)

, BCLS

Dorothee Walburga Luise Huenseler

CA1266747 014-354-870

INDIVIDUAL OWNERSHIP PLAN SHOWING PROPOSED PIPELINE R/W AND ANCILLARY SITES WITHIN THE NORTH WEST 1/4 OF SECTION 25 TOWNSHIP 80 RANGE 15 WEST OF THE 6TH MERIDIAN PEACE RIVER DISTRICT (Associated With Pipeline R/W From 7-22-81-14 To 2-25-80-15-W6M) 100 0 100 200 300 400

The intended plot size of this plan is 216mm in width by 356mm in height (Legal Size) when plotted at a scale of 1: 5,000

Caltech BC Land Surveying Inc.

Fort St. John, BC 250.263.9121 caltechgroup.com

CALTECH FILE: REFERENCE FILE: DRAFTER:

23-3072AOP20R0 23-3072APL01R0 RS/LMP

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.